New home construction in suburbia in Rock Hill, South Carolina taken from above

The Tracker

What's Actually Being Built in Florence County

A running, dated table of the subdivisions, developments and infrastructure projects we can document: what each one is, where it is, where it stands, and the public record it came from. This is a page, not a post. It gets updated; it doesn't expire.

As of October 15, 2026, HelloFlorenceSC is tracking 6 projects in Florence County: two underway (the East Montclair Way extension and the City of Florence water and sewer program), one opened (a second Chipotle on South Irby Street), one approved by the County Planning Commission with County Council's final rezoning vote not yet confirmed (a 138-lot subdivision on East Palmetto Street), one in review (Stratton Drive Townhomes), and one deferred (The Grove at Ebenezer, 219 lots).

Source document on every row Updated as things change Pending stays pending

Last verified: October 15, 2026

The Running Table

Every row below is tied to a public record — a Planning Commission agenda, a City Council packet, or a county document. Where a traffic study or a final vote hasn't happened yet, we say so rather than guessing.

East Montclair Way Extension

Underway
Status
Underway
Where
South Florence, from the end of East Montclair Way to Freedom Boulevard (US 301)
Who
Florence County project, reviewed by the City of Florence Planning Commission because it crosses city limits
Type
County road
Scale
About 650 feet (2025 plan). Funded through the Capital Project Sales Tax (CPST III). Cost and contractor have not been published.
Last action
On Oct. 12, 2026 the county said construction is well underway and a traffic signal will be installed.
Next step
WPDE reported on Oct. 9 that the road should finish within a month. The county has not given a completion date.

The Grove at Ebenezer, Phases 5A to 5C

Deferred
Status
Deferred at the applicant's request
Where
Off Ebenezer Road, Florence
Who
City of Florence. Developer Phillip Lowe.
Type
Single-family subdivision (new phases of an existing community)
Scale
219 lots. The developer has said the first section, about 28 to 30 homes, is targeted for late summer or early fall 2027.
Last action
The second-reading vote was on City Council's Sept. 14, 2026 agenda. According to the City's agenda packet, the applicant asked for it to be deferred. The packet gave no reason, and Council's minutes and video had not been posted when we checked.
Next step
No new date has been published. Council's next meeting after Sept. 14 was Oct. 12, and we have not found a record of action on this item.

Sources: City of Florence City Council agenda packet, Sept. 14, 2026 (City agenda portal)

Our coverage: Council in 5 Minutes, Sept. 14, 2026

Last checked: October 15, 2026.

Stratton Drive Townhomes

In review
Status
In review
Where
Stratton Drive, Florence (a former tennis court next to single-family homes and a church)
Who
City of Florence. Applicant: South Creek Land Co.
Type
Attached single-family townhomes
Scale
The unit count was not stated in the agenda summary we reviewed. City water and sewer are already available at the site.
Last action
On Sept. 8, 2026 the Planning Commission took up the request to annex the site and zone it NC-6.3. City staff recommended approval. The case was delayed in August so the developer could meet with neighbors. Official minutes had not been posted when we checked, so the vote is unconfirmed.
Next step
The Planning Commission makes a recommendation to City Council, and a separate sketch plan still needs approval before construction.

Sources: City of Florence Planning Commission agenda packet, Sept. 8, 2026 (City agenda portal)

Our coverage: Planning Commission recap, Sept. 8, 2026

Last checked: October 15, 2026.

Highway 76 Subdivision, 4617 East Palmetto Street

Approved by Planning Commission
Status
Approved by the Planning Commission; County Council's final rezoning vote not yet confirmed
Where
4617 East Palmetto Street, across from Francis Marion University's Griffin Athletic Complex, with both entrances on Highway 76
Who
Florence County (Council District 6). Applicant: McG Capital LLC (Browder McGill). Owner of record: S&P Campbell Enterprises, LLC.
Type
Residential subdivision with commercial frontage
Scale
138 lots on part of a 41.09-acre site. Single-family homes at the back, commercial use at the front.
Last action
The Planning Commission recommended the rezoning 9 to 0 on June 23, 2026 (front to commercial mixed-use, back to single-family residential) and approved the sketch plan at its August 2026 meeting. County Council's Sept. 17, 2026 agenda listed the rezoning (Ordinance 05-2026/27) for third reading. We have not found the result.
Next step
County Council's final vote on the rezoning. The Planning Commission only recommends, so the project depends on that vote.
Traffic study
None was required. The project engineer said both entrances on Highway 76 have turn lanes.

City Water & Sewer Overhaul (RISE Program)

Underway
Status
Underway
Where
Citywide
Who
City of Florence
Type
Water, sewer and stormwater infrastructure
Scale
Nearly $85 million for water quality improvements, part of a $138 million first round of bond funding, under a 20-year master plan
Last action
The City's June 4, 2026 update reported completed projects and work under way, including a surface water treatment plant expansion from 10 to 15 million gallons a day (the filter study has gone to state regulators) and 15,700 feet of new 30-inch water line on Freedom Boulevard. The City launched the RISE Program name for the work.
Next step
The City says it will publish updates and timelines for individual RISE projects on its Utilities page.

Second Chipotle, South Irby Street

Opened Aug. 19, 2026
Status
Opened Aug. 19, 2026
Where
2037 South Irby Street, next to the former Salvation Army thrift store
Who
City of Florence
Type
Restaurant
Scale
Restaurant with a Chipotlane pickup lane for digital orders. About 30 employees, according to our Aug. 19 report.
Last action
Opened Aug. 19, 2026. The City's Planning Commission took up the request to annex and zone the 2037 and 2111 South Irby Street parcels for commercial use in 2025, and a company representative told the Post and Courier the restaurant would open in summer 2026.
Next step
None

Know of a project we're missing, or something on this table that has since changed? Tell us — if it checks out against the record, it goes on the table and we note who flagged it.